List
by-date of authorizations and main administrative
acts regarding farms whose building process
is about to begin:
Los Siglos Wind Farm 19 mw
Zorreras Wind Farm 20 mw
La Tahuna Wind Farm 20 mw
El Bancal Wind Farm 21 mw
Total 81 mw
ADMINISTRATIVE
ACTS |
P.E.
LOS SIGLOS |
P.E.
ZORRERAS |
P.E.
LA TAHUNA |
P.E.
EL BANCAL |
| Environmental
Impact Declaration |
1/10/1999 |
31/05/2000 |
31/05/2000 |
01/10/1999 |
| Administrative
authorisation to install the wind farms
|
18/06/2001 |
19/12/2000 |
21/12/2000 |
18/06/2001
|
| Concession
of electric network connection point |
12/12/2001 |
12/12/2001 |
12/12/2001 |
12/12/2001 |
| Agreement
to approve Action Plan |
11/02/2002 |
13/02/20002 |
09/02/2002 |
14/02/2002 |
| Provincial
Commission of Urban Development and Territorial
Management agrees to approve project |
28/06/2002 |
28/06/2002 |
28/06/2002 |
28/06/2002 |
| Provincial
Commission of Urban Development and Territorial
Management agrees to approve the Tarifa
Wind Farm facility management Special
Plan |
28/06/2002 |
28/06/2002 |
28/06/2002 |
28/06/2002 |
| Tarifa
Townhall grants permission to start building
|
31/07/2002 |
31/07/2002 |
31/07/2002 |
31/2002
|
| Directorate
General of Industry, Energy and Mining
agrees to grant the farms a Special Regime
status |
24/03/2003 |
24/03/2003 |
24/03/2003 |
24/03/2003 |
| Tarifa
Townhall agrees to grant a 6 month extension
for building starting date |
06/05/2003 |
06/05/2003 |
06/05/2003 |
06/05/2003 |
Lands where the Tarifa wind farms
will be located, in the area of the Almarchal: